Construction and Maintenance Projects



Library Addition
Projected Completion: Fall 2025
The new library addition involves the construction of a new 24,000 sq. ft. building that will be connected to the existing library by a pedestrian walkway on the second floor.
Construction is in the final phase
Current Projects
Click on plus button at the bottom of this Accordion BLOCK (not accordion tab) to create a new tab. Select Accordion TAB block to edit tab headline. Select nested blocks within accordion tab to edit content.
-
Project Cost: $21,000,000
Status: In final phase of the project
Estimated Completion Date: Fall 2025
-
Project Cost: $ 1,100,000
Status: In the construction phase
Estimated Completion Date: Fall 2025
-
Project Cost: $250,000
Status: In final phase of the project
Estimated Completion Date: Fall 2025
-
Project Cost: $3,000,000
Status: In the construction phase
Estimated Completion Date: Spring 2026
-
Project Cost: $ 225,000
Status: In the construction phase
Estimated Completion Date: Winter 2026
Completed Projects
Click on plus button at the bottom of this Accordion BLOCK (not accordion tab) to create a new tab. Select Accordion TAB block to edit tab headline. Select nested blocks within accordion tab to edit content.
-
Project Cost: $1,075,000
Status: Completed, Summer 2025
-
Project Cost: $ 322,000
Status: Completed, Summer 2025
-
Project Cost: $ 654,000
Status: Completed, Summer 2025
-
Project Cost: $ 706,000
Status: Completed, Summer 2024
-
Project Cost: $ 1,674,000
Status: Completed, Summer 2025
Future Projects
Click on plus button at the bottom of this Accordion BLOCK (not accordion tab) to create a new tab. Select Accordion TAB block to edit tab headline. Select nested blocks within accordion tab to edit content.
-
Project Cost: $3,586,300
Status: Anticipated, Spring 2027 (Includes the new driveway, Valley Falls Road turn lanes, landscaping, digital sign and gateway structure)
-
Project Cost: $ 185,000
Status: Anticipated, Fall 2025
-
Project Cost: $ 1,344,500
Status: Anticipated, Summer 2026, Summer 2027
-
Project Cost: $ 11,500,000
Status: Anticipated, Fall 2027 (estimated completion date)
-
Project Cost: $ 300,000
Status: Anticipated, Summer 2026
-
Project Cost: $ 645,000 (we will be reimbursed by ETV)
Status: Anticipated, TBA
-
Project Cost: $ 42,000,000
Status: Anticipated, TBA
-
Project Cost: $ 2,290,500
Status: Anticipated, Summer 2026
-
Project Cost: $ 63,000
Status: Anticipated, Summer 2026
-
Project Cost: $ 6,250,000
Status: Anticipated, Summer 2027